Spares delivery delay means Manthatisi will go back in the water in June |
Publication |
defenceWeb |
Date | 2014-05-27 |
Reporter | Kim Helfrich |
Web link | www.defenceweb.co.za |
A delay in delivery of certain spare and
replacement parts means SAS Manthatisi
(S101) is still on the synchrolift at the
Simon’s Town naval dockyard and is not yet
in the water.
The Type 209 diesel electric submarine was
one of three acquired by the Navy as part of
the 1998 Strategic Defence Procurement
Package (SDPP) and was commissioned in
November 2005. She has been out of service
since 2007 following what was then reported
to Parliament as damage to the boat’s
electrical systems when “someone” connected
the submarine to its high voltage shore
service “the wrong way round”.
Last month Flag Officer Fleet (FOF) Rear
Admiral Bravo Mhlana told defenceWeb that
Manthatisi left the shed, where she
underwent major refit and overhaul work, on
April 11. She was due to be put back into
the water on May 5. This has not happened, a
source said, due to a delay in certain parts
being delivered to South Africa.
The source indicated planning, at this
stage, was for Manthatisi to go back into
the water “early in June” with a tentative
commissioning date of August 15 set
following sea trials.
Part of the refit saw S101 fitted with 480
new man-sized battery cells weighing 250
tons at a cost of around R250 million.
Navy watchers maintain the delays
experienced were “normal” because it was the
first of type to undergo such major work.
“This meant a steep learning curve for both
the Navy and the Naval Dockyard. It must
also be remembered the refit did not
commence immediately after she came out of
the water. It was delayed to allow it to fit
into the new scheduled maintenance cycle.
This means once she is operational again,
the next submarine will move into the
maintenance and overhaul schedule,” the
source said.
The refit and overhaul work is in accordance
with laid down schedules for the Type 209
submarine as well as being in line with the
Navy business plan for its underwater craft.
With acknowledgement to
Kim Helfrich and defenceWeb.
Funding is certainly a
major factor in this matter, but not the
only one.
No one outside the establishment is saying
what really happened and what is still to
happen.
And the implications of the incorrect
recharging procedure are certainly greater
than R200 000.
For one, the boat was only operational for
two years after commissioning before it was
critically damaged. This should be about 7
to 15 years, depending on its use profile.
And the cost of the replacement batteries is
not R250 million, it is more like R35
million, maybe R50 million. The balance is
partly repair work and partly refit work.
But no one other than on the very inside
knows these details.
It was decided only to repair this damage
during the first refit because there was no
other way of getting funding.
As Lieutenant-General Steyn testified at the
APC a little more than a week ago, there was
no funding in the SPDs for anything other
than acquisition costs.
But it is not correct that the boat is going
through a normal use/maintenance profile.
It will be interesting to see whether she
goes back into full operational state after
the current work.
Actually, this matter needs to be fully and
transparently ventilated in a board of
enquiry and not by unofficial inferential
means as has been the case since 2007.